Project Title: HATCH – Independent valuation of Transnet Freight Rail network Infrastructure assets
Project duration: 2018-2019
Project location:
Project costs: R2mil
Type of appointment: Sub- consultant to the main consultant (Hatch)
Client: Public/ Government (Transnet)
Summary of project scope
The project is for the assessment of Transnet Freight Rails’ infrastructure assets on four main lines, namely:
Kaapmuiden to Barberton
Empangeni to Durban
Potchefstroom to Kimberley
Sishen to Halfweg
The assets that were assessed include track superstructure and substructure, culverts, bridges, tunnels, network-related buildings, level crossings, OHTE, substations, colour light signalling etc.
Elwatini’s responsibility involved the culvert, level crossing and signage assessments. A sample of culverts and level crossing were inspected in each main line and the condition